Deep Water Survey
A Deep Water Survey was performed on a double-lined brine pond with a geonet between the secondary and primary geomembranes. The pond was approximately 19,000 meters in size.The pond was surveyed at full capacity with 52,000 cubic meters of solution in the lined area. During the survey, brine water was placed between liners in order to have an electrical media above and below the primary geomembrane being surveyed.
Deep Water Survey
Deep Water Survey
Comments
Post a Comment